EXECUTIVE SUMMARY

I.      Introduction

This is the 50th Monthly EM&A Report prepared by Fugro Technical Services Limited for the Contract No. HY/2018/08 Central Kowloon Route ¡V Central Tunnel. The Contract No. HY/2018/08 commenced on 19 September 2019. This report summarized the monitoring results and audits findings of the EM&A programme under the issued EP (EP No.: EP-457/2013/D) and in accordance with the EM&A Manual during the reporting period from 01/10/2023 to 31/10/2023.

 

II.      Summary of Main Works Undertaken and Key Measures Implemented

The main construction works carried out in the reporting period were as follow:

 

Ho Man Tin

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Struct installation and D-wall coring;

¡P          ELS excavation;

¡P          Site and shaft installation.

 

Yau Ma Tei

¡P          Drill and break excavation;

¡P          Drill and blast excavation;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Mucking out from tunnel;

¡P          Site and shaft installation.

 

Ma Tau Kok

¡P          Drill and break excavation;

¡P          TBM pilot tunnel enlargement;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction

¡P          Mucking out from tunnel and horizontal access;

¡P          Site and shaft installation.

 

Kai Tak Barging Point

¡P          Spoil handling and disposal.

 

Sheung Lok Street

¡P          Concreting and importing fill material by drop pipe.

 

Ma Hang Chung Road

¡P          Concreting.

 

III.      Summary of Exceedances, Investigation and Follow-up

No Action and Limit Level exceedance was recorded for construction dust monitoring in the reporting month.

 

Four (4) Action Level exceedance was recorded for construction noise due to the noise-related complaints received in the reporting month. No Limit Level exceedance was recorded for construction noise monitoring in the reporting month.

 

IV.      Complaint Handling, Prosecution and Public Engagement.

All complaints received in the last reporting month were finalized.

 

Four (4) noise-related complaints (i.e. 2nd , 22nd , 24th and 26th October 2023) were received in the reporting month.

 

The complaint cases in October 2023 are summarized in Table I.

 

Table I    Environmental Complaints Log

Complaint Log No.

Date of Complaint

Received From

Nature of Complaint

Status

EC176_CKRCT20231002_721

2nd October 2023

The Contractor Hotline

Construction noise

Investigation report was finalized on 9th November 2023.

EC177_CKRCT20231024_729

24th October 2023

The Contractor Hotline

Construction noise

Under investigation and the investigation results will be reported in the subsequent Monthly EM&A Report.

EC178_CKRCT20231022_730

22nd October 2023

1823

Construction noise

Investigation report was finalized on 9th November 2023.

EC179_CKRCT20231026_734

26th October 2023

The Contractor Hotline

Construction noise

Under investigation and the investigation results will be reported in the subsequent Monthly EM&A Report.

No notification of summons and prosecutions were received in the reporting period.

 

No public engagement activities were conducted in the reporting period.

 

V.      Reporting Change

There were no reporting changes during the reporting month.

 

VI.      Future Key Issues

The main works will be anticipated in the next reporting period are as follow:

 

Ho Man Tin

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Struct installation and D-wall coring;

¡P          ELS excavation;

¡P          Site and shaft installation.

 

Yau Ma Tei

¡P          Drill and break excavation;

¡P          Drill and blast excavation;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Mucking out from tunnel;

¡P          Site and shaft installation.

 

Ma Tau Kok

¡P          Drill and break excavation;

¡P          TBM pilot tunnel enlargement;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OVHD construction;

¡P          Mucking out from tunnel and horizontal access;

¡P          Site and shaft installation.

 

Kai Tak Barging Point

¡P          Spoil handling and disposal.

 

Sheung Lok Street

¡P          Concreting and importing fill material by drop pipe.

 

Ma Hang Chung Road

¡P          Concreting.

 

The recommended mitigation measures corresponding to the main works in the next reporting period are listed as follow:

¡P          Good relationship shall be maintained with the nearby sensitive receivers/ stakeholders which may be affected by the construction works such as providing better/ more detail information of the work nature and inform in advance of the works to the nearby residents;

¡P          Any excavated, stockpile of dusty material or load of dusty materials on a vehicle leaving a construction site should be covered entirely by impervious sheeting;

¡P          All construction plants / machineries should be checked / serviced on a regular basis during the courses of construction to minimize the emission of noise generation and eliminate dark smoke emission;

¡P          All C&D materials generated should be transported and stored at temporary storage area. Suitable materials should be sorted for reuse on-site;

¡P          Every vehicle shall be cleaned thorough at the designated wheel washing area onsite;

¡P          Wastewater generated from drilling shall be properly collected for reuse or treated by wastewater treatment facilities before discharge;

¡P          Provision of drip trays for equipment likely cause spillage of chemical / fuel, and provide routine maintenance;

¡P          Erecting temporary noise barrier for noisy Powered Mechanical Equipment (PME) and deployment of Quality Powered Mechanical Equipment (QPME) as many as practicable;

¡P          Conditions in the Environmental Permit and License should be followed;

¡P          All recommended mitigation measures specified in the approved EIA Report and EM&A Manual shall be implemented;

¡P          All vehicles should be cleaned before leaving the construction site to ensure no muddy deposited by them on roads.

 

The following EP submissions were submitted during the reporting month:

 

Table II   Status of Required Submission under Environmental Permit

EP Condition

Submission

Submission Date

3.4

Monthly EM&A Report (September 2023)

  13 October 2023

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contents

EXECUTIVE SUMMARY  iii

1.          INTRODUCTION   1

1.1       Background  1

1.2       Project Organization  2

1.3       Construction Programme and Activities  2

1.4       Works undertaken during the month  2

1.5       Status of Environmental Licences, Notification and Permits  2

2.         ENVIRONMENTAL MONITORING REQUIREMENTS  4

2.1       Construction Dust and Noise Monitoring Location  4

2.2       Construction Dust Monitoring  5

2.3       Construction Noise Monitoring  7

2.4       Construction Dust and Noise Monitoring Schedule  8

2.5       The Action and Limit Levels  8

2.6       Landscape and Visual 8

3.         ENVIRONMENTAL MONITORING RESULTS  9

3.1       Construction Dust Monitoring  9

3.2       Construction Noise Monitoring  9

3.3       Waste Management 10

3.4       Landscape and Visual 10

4.         ENVIRONMENTAL SITE INSPECTION AND AUDIT  11

5.         ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE  12

5.1       Complaint Handling, Prosecution and Public Engagement 12

5.2       Summary of Environmental Non-Compliance  12

5.3       Summary of Monitoring Exceedance  12

6.         IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURE  13

7.         FUTURE KEY ISSUES  14

8.         CONCLUSION AND RECOMMENDATIONS  16

 

 

 

 

 

Tables

Table I ¡V Environmental Complaints Log  ii

Table II ¡V Status of Required Submission under Environmental Permit iii

Table 1.1 ¡V Contact Information of Key Personnel 2

Table 1.2 ¡V Environmental Licenses, Notification and Permits Summary  2

Table 2.1 ¡V Construction Dust and Noise Monitoring Location  3

Table 2.2 ¡V Construction Dust Monitoring Equipment 3

Table 2.3 ¡V Construction Noise Monitoring Parameters, Frequency and Duration  6

Table 2.4 ¡V Construction Noise Monitoring Equipment 6

Table 3.1 ¡V Summary of 1-hour TSP Monitoring Results in the Reporting Period  8

Table 3.2 ¡V Summary of 24-hour TSP Monitoring Results in the Reporting Period  8

Table 3.3 ¡V Summary of Construction Noise Monitoring Results in the Reporting Period  8

Table 4.1 ¡V Observations and Recommendation of Site Inspection in the Reporting Period  10

Table 5.1 ¡V Environmental Complaints Log  12

Table 6.1 ¡V Status of Required Submission under Environmental Permit 14

 

Figures

Figure 1        The Site Layout Plan of the Contract  

Figure 2.1     The Location of the Construction Dust and Noise Monitoring Stations (Ho Man Tin)

Figure 2.2    The Location of the Construction Dust and Noise Monitoring Stations (Ma Tau Kok)

Figure 2.3    The Location of the Construction Dust and Noise Monitoring Stations (Yau Ma Tei)

 

 

Appendices

Appendix A  Construction Programme

Appendix B  Project Organization Chart

Appendix C  Calibration Certificate for Construction Dust Monitoring Equipment

Appendix D Calibration Certificate for Construction Noise Monitoring Equipment

Appendix E  Environmental Monitoring Schedule

Appendix F  Action and Limit Levels for Construction Dust and Noise Monitoring

Appendix G  Construction Dust Monitoring Results and Meteorological Observations

Appendix H Construction Noise Monitoring Results

Appendix I   Event and Action Plan

Appendix J   Implementation Status of Environment Mitigation Measures (Construction Phase)

Appendix K  Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

Appendix L  Waste Flow Table


1       INTRODUCTION

1.1       Background

1.1.1      In order to meet the traffic demand and relieve traffic congestion on the existing east-west roads across Central Kowloon, Central Kowloon Route (CKR) (hereinafter referred to as ¡§the Project¡¨) is proposed which is a 4.7 km long dual 3-lane trunk road in Central Kowloon linking Yau Ma Tei Interchange in West Kowloon with the road network on Kai Tak Development and Kowloon Bay in East Kowloon.

1.1.2      The Central Kowloon Route ¡V Design and Construction Environmental Impact Assessment Report (Register No.: AEIAR-171/2013) was approved with conditions by the Environmental Protection Department (EPD) on 11 July 2013. An Environmental Permit (EP-457/2013) was issued on 9 August 2013. A variations of EP (VEP-594/2021) was applied on 26 May 2021 and the latest EP (EP-457/2013/D) was issued by EPD on 15 June 2021.

1.1.3      Contract No. HY/2018/08 Central Kowloon Route ¡V Central Tunnel (hereinafter referred to as ¡§the Contract¡¨), is one of the contracts of CKR which included the construction of the central tunnel, cut-and-cover tunnels at Yau Ma Tei and Ma Tau Kok and construction of piles and diaphragm walls for Ho Man Tin ventilation building.

1.1.4      Fugro Technical Services Limited (FTS) was appointed by Bouygues Travaux Publics (BTP) as the Environmental Team (ET) under the Contract no. HY/2018/08) to execute the environmental monitoring and audit (EM&A) programme under the issued EP (EP No.: EP-457/2013/D) and in accordance with the EM&A Manual.

1.1.5      This is the 50th Monthly EM&A Report prepared by FTS for the Contract No. HY/2018/08 Central Kowloon Route ¡V Central Tunnel. The Contract No. HY/2018/08 commenced on 19 September 2019. This report summarized the monitoring results and audits findings of the EM&A programme under the issued EP (EP No.: EP-457/2013/D) and in accordance with the EM&A Manual during the reporting period from 1/10/2023 to 31/10/2023.

1.2      Project Organization

1.2.1      The Project Organization structure is shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.1.

Table 1.1                Contact Information of Key Personnel

Party

Position

Name

Telephone

Highways Department (HyD)

E13/CKR

Mr. Joe Lam

2762 3380

Arup-Mott MacDonald Joint Venture (AMMJV)

Senior Resident Engineer

Mr. Ben Poon

3619 5967

ERM-Hong Kong, Limited (ERM)

Independent Environmental Checker (IEC)

Ms. Mandy To

2271 3000

Bouygues Travaux Publics (BTP)

Environmental Manager

Mr. Simon Wong

9281 4346

Fugro Technical Services Limited

ET Leader

Mr. Calvin Leung

3565 4441

 

1.3      Construction Programme and Activities

1.3.1      The construction phase of this Contract under the EP commenced in October 2019. The site layout plan of the Contract is shown in Figure 1.

1.3.2      The construction programme of this Contract is shown in Appendix A.

1.4      Works undertaken during the month

1.4.1      The main construction works carried out in the reporting period were as follow:

Ho Man Tin

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Struct installation and D-wall coring;

¡P          ELS excavation

¡P          Site and shaft installation.

 

Yau Ma Tei

¡P          Drill and break excavation;

¡P          Drill and blast excavation;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Mucking out from tunnel;

¡P          Site and shaft installation.

 

Ma Tau Kok

¡P          Drill and break excavation;

¡P          TBM pilot tunnel enlargement;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction

¡P          Mucking out from tunnel and horizontal access;

¡P          Site and shaft installation.

 

Kai Tak Barging Point

¡P          Spoil handling and disposal.

 

Sheung Lok Street

¡P          Concreting and importing fill material by drop pipe.

 

Ma Hang Chung Road

¡P          Concreting.

 

1.5      Status of Environmental Licences, Notification and Permits

1.5.1      A summary of the relevant permits, licenses and/or notifications on environmental protection for this Contract is presented in Table 1.2.

Table 1.2                Environmental Licenses, Notification and Permits Summary

Permit/ Notification/ License

Reference No

Valid From

Valid Till

Form NB

448930, 448970, 448971

Mid-Sep 2019

NA

Billing Account for Disposal of C&D waste

Account no. 7034790

06 Aug 2019

NA

Chemical Waste Producer Registration (Ho Man Tin Construction site)

5111-236-B2557-02

25 Sep 2019

NA

Chemical Waste Producer Registration (Yau Ma Tei Construction site)

5213-225-B2557-05

19 Apr 2021

NA

Chemical Waste Producer Registration (Ma Tau Kok Construction site)

5213-247-B2557-06

19 Apr 2021

NA

Construction Noise Permit

Construction Noise Permit (Ho Man Tin Construction site)1

GW-RE0813-23

24 Jul 2023

23 Oct 2023

Construction Noise Permit (Ho Man Tin Construction site)

GW-RE1124-23

14 Sep 2023

13 Nov 2023

Construction Noise Permit (Yau Ma Tei Construction site)2

GW-RE0790-23

13 Jul 2023

12 Oct 2023

Construction Noise Permit (Yau Ma Tei Construction site)

GW-RE1281-23

13 Oct 2023

12 Jan 2023

Construction Noise Permit (Yau Ma Tei Construction site)

GW-RE1183-23

23 Sep 2023

22 Dec 2023

Construction Noise Permit (Ma Tau Kok Construction site)

GW-RE0891-23

4 Aug 2023

03 Nov 2023

Construction Noise Permit (Ma Tau Kok Construction site)3

GW-RE0956-23

18 Aug 2023

17 Oct 2023

Construction Noise Permit (Ma Tau Kok Construction site)

GW-RE1271-23

18 Oct 2023

17 Dec 2023

Construction Noise Permit (Kai Tak Barging Point)

GW-RE0547-23

01 Jun 2023

30 Nov 2023

Construction Noise Permit (Sheung Lok Street)

GW-RE0954-23

18 Aug 2023

13 Nov 2023

Water Discharge License

Water Discharge License

 

WT00034873-2019

(Ho Man Tin Construction site)

22 Nov 2019

30 Nov 2024

WT00035436-2019

(Portion 18)

02 Apr 2020

30 Apr 2025

WT00037723-2021

(Yau Ma Tei Construction site)

07 Apr 2021

30 Apr 2026

WT00037883-2021

(Ma Tau Kok Construction site)

30 Apr 2021

30 Apr 2026

WT00042304-2022

(Sheung Lok Street)

13 Oct 2022

31 Oct 2027

 



 

 

Notes:

1 GW-RE0813-23 was superseded by GW-RE1124-23 since 14 September 2023.

2 GW-RE0790-23 was superseded by GW-RE1281-23 since 13 October 2023.

3 GW-RE0956-23 was superseded by GW-RE1271-23 since 18 October 2023.

 

 

2      ENVIRONMENTAL MONITORING REQUIREMENTS

2.1      Construction Dust and Noise Monitoring Locations

2.1.1      Three construction dust monitoring locations and five construction noise monitoring locations pertinent to the Project have been identified based on the approved EM&A Manual for the Project. The locations of the construction dust and noise monitoring stations are summarized in Table 2.1 as displayed in Figures 2.1 - 2.3.

 

Table 2.1                             Construction Dust and Noise Monitoring Locations

Dust Monitoring Station ID

Noise Monitoring Station ID

Monitoring Location

M-A3

M-N3

SKH Tsoi Kung Po Secondary School

/

E-N12a

19 Hing Yan Street

E-A14a

E-N21a

Block B of Merit Industrial Centre

W-A6

/

Man Cheong building

/

W-N18

Hydan Place

/

W-N25A

Prosperous Garden Block 1

Notes:

1. The dust and noise monitoring stations proposed in the EM&A Manual for M-A6/ M-N6 (i.e. Ko Fai House, Kwun Fai Court) was not available for impact dust and noise monitoring, therefore impact monitoring was conducted at M-A3/ M-N3 as an alternative which was agreed by the ER, IEC and EPD;

2. The noise monitoring station proposed in the EM&A Manual for E-N12 (i.e. Grand Waterfront Tower 3) was not available for impact dust and noise monitoring, therefore impact monitoring was conducted at E-N12a as an alternative which was agreed by the ER, IEC and EPD;

3. The dust and noise monitoring stations proposed in the EM&A Manual for E-A14 (i.e. Wyler Gardens) and E-N21 (i.e Hang Chien Court Block J) was not available for impact dust and noise monitoring, therefore impact monitoring was conducted at E-A14a/ E-N21a as an alternative which was agreed by the ER, IEC and EPD;

4. The dust monitoring stations proposed in the EM&A Manual for W-A5 (i.e. The Coronation) was not available for impact dust monitoring, therefore impact monitoring was conducted at W-A6 as an alternative which was agreed by the ER, IEC and EPD.

 

2.1.2      The construction dust and noise monitoring locations at M-A3 and M-N3 are covered by Contract No. HY/2018/08 Central Kowloon Route ¡V Central Tunnel whereas the construction dust and noise monitoring locations at E-A14a, E-N12a and E-N21a are now covered by Contract No. HY/2014/07 Central Kowloon Route ¡V Kai Tak West. The monitoring results at E-A14a, E-N12a and E-N21a in the reporting month are presented in the monthly EM&A Report prepared by Contract No. HY/2014/07.

 

2.1.3      The construction dust and noise monitoring locations at W-A6, W-N18 and W-N25A are now covered by Contract No. HY/2014/08 Central Kowloon Route ¡VYau Ma Tei East. The monitoring results at W-A6, W-N18 and W-N25A in the reporting month are presented in the monthly EM&A Report prepared by Contract No. HY/2014/08.

2.2     Construction Dust Monitoring

Monitoring Requirement

2.2.1      In accordance with the approved EM&A Manual, 1-hour and 24-hour Total Suspended Particulates (TSP) levels should be measured at the designated air quality monitoring stations to indicate the impacts of construction dust on air quality. Regular Impact 24-hour TSP monitoring should be carried out for at least once every 6 days, and 1-hour TSP monitoring should be done at least 3 times every 6 days when the highest dust impact occurs.

Monitoring Equipment

2.2.2      24-hour TSP air quality monitoring was performed using High Volume Sampler (HVS) deployed at the designated monitoring station. The HVS shall meet all the requirements of the EM&A Manual.

2.2.3      A portable direct reading dust meter was used to carry out the 1-hour TSP monitoring.

2.2.4      The model of the dust monitoring equipment used is summarized in Table 2.2.

Table 2.2                Construction Dust Monitoring Equipment

Equipment

Brand

Model

Serial No.

High Volume Sampler

(24-hour TSP)

Tisch

TE-5170

4388

Calibrator

Tisch

TE-5025A

2456

Portable direct reading dust meter (1-hour TSP)

Sibata

LD-5R

882147

 

Monitoring Methodology for HVS

2.2.5      The following guidelines were adopted during the installation of HVS:

 

¡P              Sufficient support is provided to secure the samplers against gusty wind.

¡P              No two samplers are placed less than 2 meters apart.

¡P              The distance between the sampler and an obstacle, such as buildings, is at least twice the height that the obstacle protrudes above the sampler.

¡P              A minimum of 2 meters of separation from walls, parapets and penthouses is required for rooftop samples.

¡P              A minimum of 2 meters separation from any supporting structure, measured horizontally is required.

¡P              No furnaces or incineration flues are nearby.

¡P              Airflow around the samplers is unrestricted.

¡P              The samplers are more than 20 meters from the drip line.

¡P              Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.

¡P              Permission must be obtained to set up the samplers and to obtain access to the monitoring stations.

¡P              A secured supply of electricity is needed to operate the samplers.

2.2.6      Prior to the commencement of the dust sampling, the flow rate of the high volume sampler shall be properly set. The power supply should be checked to ensure the proper functioning of the sampler. The sampler is recommended to be operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station.

2.2.7      The filter holding frame should be removed by loosening the four nuts and placing carefully a weighted and conditioned filter at the centre with the stamped number upwards on a supporting screen.

2.2.8      The filter should be aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter. The filter holding frame should be tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges.

2.2.9      A programmed timer should be used to control the duration of operation. Information should be recorded on the record sheet, which included the starting time, the weather condition and the filter number.

2.2.10    After sampling process is finished, the filter should be removed and sent to the laboratory for weighting. The elapsed time should also be recorded.

2.2.11    All filters should be equilibrated in a conditioning environment for 24 hours before weighting. The conditioning environment temperature should be between 25¢XC and 30¢XC and not vary by more than ¡Ó3¢XC; the relative humidity (RH) should be <50% and not vary by more than ¡Ó5%. A convenient working RH is 40%.

Maintenance and Calibration for HVS

2.2.12    The high volume motors and their accessories should be properly maintained, including routine motor brushes replacement and electrical wiring checking, to ensure that the equipment and a continuous power supply were in good working condition.

2.2.13    Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at fortnightly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The calibration certificate for the HVS is provided in Appendix C.

Monitoring Methodology for Direct Reading Dust Meter

2.2.14    Portable Laser Particle Photometer Monitors should be operated in accordance with the Manufacturer¡¦s instruction Manual as below:

a) Pulling up the air sampling inlet cover

b) Changing the Mode 0 to BG

c) Pressing Start/Stop switch

d) Turning the knob to SENSI.ADJ and press it

e) Pressing Start/Stop switch again

f) Returning the knob to the position MEASURE slowly

g) Pressing the timer set switch to set measuring time

h) Removing the cap and start the measurement

Maintenance and Calibration for Direct Reading Dust Meter

2.2.15    ET shall submit sufficient information to the IEC to prove that the instrument is capable of achieving comparable results to the HVS. The instrument should also be calibrated regularly, and the 1-hour sampling shall be determined periodically by the HVS to check the validity and accuracy of the results measured by direct reading method. The calibration certificate for the direct reading dust meter is provided in Appendix C.

2.3     Construction Noise Monitoring

Monitoring Requirement

2.3.1      In accordance with the EM&A Manual, impact noise monitoring should be conducted at the designated noise monitoring stations for at least once a week during the construction phase of the Project. The parameters, frequency and duration of impact noise monitoring is summarized in Table 2.3.

 

Table 2.3                Construction Noise Monitoring Parameters, Frequency and Duration

Parameter

Duration

Frequency

A-weighted equivalent continuous sound pressure level (Leq). L10 and L90 were also recorded

30 minutes

At least once per week

 

 

Monitoring Equipment

2.3.2      Noise monitoring was performed using sound level meter at the designated monitoring station. The sound level meters deployed comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.

2.3.3      The model of the noise monitoring equipment used is summarized in Table 2.4.

Table 2.4                Construction Noise Monitoring Equipment

Equipment

Brand

Model

Serial No.

Acoustic Calibrator

Casella

CEL-120/1

2092809

Sound Level Meter

Casella

CEL-63X

4181568

 

Monitoring Methodology

2.3.4      Noise measurement should be conducted as the following procedures:

 

a) Free field measurements were made at monitoring location M-N3. A correction of +3 dB(A) shall be made to the free field measurements.

b) The battery condition should be checked to ensure good functioning of the meter.

c) Parameters such as frequency weighting, the time weighting and the measurement time should set as follow:

 

(i)      Frequency weighting: A

(ii)     Time weighting: Fast

(iii)    Measurement time: 30 minutes

 

d) Prior to and after noise measurement, the meter shall be calibrated using the calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement will be considered invalid and repeat of noise measurement is required after re-calibration or repair of the equipment.

e) The wind speed at the monitoring station shall be checked with the portable wind meter. Noise monitoring should be cancelled in the presence of fog, rain, and wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.

f) Noise measurement should be paused during periods of high intrusive noise if possible and observation shall be recorded when intrusive noise is not avoided.

g) At the end of the monitoring period, the Leq, L10 and L90 should be recorded. In addition, site conditions and noise sources should also be recorded on a standard record sheet.

 

Maintenance and Calibration

2.3.5      Maintenance and calibration procedures should also be carried out, including:

a) The microphone head of the sound level meter and calibrator should be cleaned with a soft cloth at quarterly intervals.

b) The sound level meter and calibrator should be calibrated annually by a HOKLAS laboratory or the manufacturer.

The calibration certificates for noise monitoring equipment are provided in Appendix D.

2.4     Construction Dust and Noise Monitoring Schedule

2.4.1      The environmental monitoring schedule for the reporting period is provided in Appendix E.

2.5     The Action and Limit Levels

2.5.1      The Action and Limit Levels for construction dust and noise monitoring are provided in Appendix F.

2.6     Landscape and Visual

2.6.1      As per the EM&A Manual, the landscape and visual mitigation measures shall be implemented and site inspections should be undertaken once every two weeks during the construction period. A summary of the implementation status is presented in Section 4.


3      ENVIRONMENTAL MONITORING RESULTS

3.1      Construction Dust Monitoring

3.1.1      The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Table 3.1 and Table 3.2 respectively. Detailed construction dust monitoring results and daily extract of meteorological observations are presented in Appendix G.

3.1.2      The monitoring results at E-A14a and W-A6 are reported in the monthly EM&A Reports prepared by Contract No. HY/2014/07 and Contract No. HY/2014/08 respectively.

Table 3.1                Summary of 1-hour TSP Monitoring Results in the Reporting Period

Station ID

Average (µg/m3)

Range (µg/m3)

Action Level (µg/m3)

Limit Level (µg/m3)

M-A3

47

63 - 92

333

500

Table 3.2                Summary of 24-hour TSP Monitoring Results in the Reporting Period

Station ID

Average (µg/m3)

Range (µg/m3)

Action Level (µg/m3)

Limit Level (µg/m3)

M-A3

57

44 - 78

153

260

 

3.1.3      No Action and Limit Level exceedance was recorded for 1-hour TSP monitoring and 24-hour TSP monitoring at the monitoring location in the reporting month.

3.1.4      Major dust sources during the monitoring included nearby traffic emission.

3.1.5      The Event and Action Plan for the construction dust monitoring is given in Appendix I.

3.2     Construction Noise Monitoring

3.2.1      The monitoring results for noise are summarized in Table 3.3 and the monitoring data is given in Appendix H.

3.2.2      The monitoring results at E-N12a, E-N21a, W-N18 and W-N25A are reported in the monthly EM&A Reports prepared by Contract No. HY/2014/07 and Contract No. HY/2014/08 respectively.

Table 3.3                Summary of Construction Noise Monitoring Results in the Reporting Period

Station ID

Date

1Measured Noise Level, dB(A), Leq (30 mins)

 2Corrected Noise Level, dB(A), Leq (30 mins)

Action Level

Limit Level dB(A), Leq (30 mins)

M-N3

05 Oct 2023

69.5

N/A

When one documented complaint is received

For Schools:

70dB(A) during normal teaching period and 65 dB(A) during examination periods

11 Oct 2023

69.1

N/A

16 Oct 2023

63.4

N/A

26 Oct 2023

64.8

N/A

Notes:    

1.     Free field noise levels were adjusted with a correlation of +3 dB(A);

2.     Corrected Noise Level =10* log (10^ (Measured Noise Level/10) ¡V 10^ (Baseline Noise Level/10)), where the Baseline Noise Level = 67.7 dB(A).

3.2.3      No Limit Level exceedance was recorded for construction noise monitoring at the monitoring location in the reporting month. 

3.2.4      Four (4) Action Level exceedance was recorded for construction noise due to the noise-related complaints received in the reporting month.

3.2.5      Major noise sources during the monitoring included nearby traffic noise.

3.2.6      The Event and Action Plan for the construction noise monitoring is given in Appendix I.

3.3     Waste Management

3.3.1      Auditing of waste management practices during regular site inspections confirmed that the waste generated during construction were properly, stored, handled and disposed of in general. The Contractor was responsible for the implementation of any mitigation measures to reduce waste or redress issues arising from the waste materials.

3.3.2      The implemented environmental mitigation measures for the waste management in the reporting period are summarized in Appendix J. The summary of observations and recommendations made for waste management during the site inspections are presented in Table 4.1.

3.3.3      Monthly summary of waste flow table is detailed in Appendix L.

3.4     Landscape and Visual

3.4.1      Bi-weekly inspections of the implementation of landscape and visual mitigation measures were conducted on 10 and 24 October 2023. The implementation the landscape and visual mitigation measures in the reporting period are summarized in Appendix J. The summary of observations and recommendations made for landscape and visual mitigation measures during the site inspections are presented in Table 4.1.

3.4.2      The Event and Action Plan for landscape and visual during construction phase is given in Appendix I.


4     ENVIRONMENTAL SITE INSPECTION AND AUDIT

4.1.1      Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. A summary of the mitigation measures implementation status is provided in Appendix J.

4.1.2      In the reporting month, five site inspections were carried out on 3, 10 (with IEC), 17, 24 and 31 October 2023. Details of observations recorded during the site inspections are presented in Table 4.1.

Table 4.1                Observations and Recommendation of Site Inspection in the Reporting Period

Environmental Aspect

Date

Observations and Recommendations

Follow-up Actions

Air Quality

Nil

Nil

Nil

Nil

Nil

Nil

Noise

Nil

Nil

Nil

Water Quality

Nil

Nil

Nil

Waste Management

Nil

Nil

Nil

Landscape and Visual

Nil

Nil

Nil

Permit/ Licenses

24th October 2023

NRMM label shell be provided on the generator.

The item was rectified by the Contractor on 24th October 2023.

 


 

5      ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE

5.1      Complaint Handling, Prosecution and Public Engagement

5.1.1      All complaints received in the last reporting month were finalized.

5.1.2      Four (4) noise-related complaints (i.e. 2nd , 22nd , 24th and 26th October 2023) were received in the reporting month.

5.1.3      The complaint cases in October 2023 are summarized in Table 5.1.

Table 5.1                Environmental Complaints Log

Complaint Log No.

Date of Complaint

Received From

Nature of Complaint

Status

EC176_CKRCT20231002_721

2nd October 2023

The Contractor Hotline

Construction noise

Investigation report was finalized on 9th November 2023.

EC177_CKRCT20231024_729

24th October 2023

The Contractor Hotline

Construction noise

Under investigation and the investigation results will be reported in the subsequent Monthly EM&A Report.

EC178_CKRCT20231022_730

22nd October 2023

1823

Construction noise

Investigation report was finalized on 9th November 2023.

EC179_CKRCT20231026_734

26th October 2023

The Contractor Hotline

Construction noise

Under investigation and the investigation results will be reported in the subsequent Monthly EM&A Report.

 

5.1.4                 Cumulative complaint log, summaries of complaints, notification of summons and successful prosecutions are presented in Appendix K.

5.1.5                 No public engagement activities were conducted in the reporting period.

5.2     Summary of Environmental Non-Compliance

5.2.1                 No environmental non-compliance was recorded in the reporting period

5.3     Summary of Monitoring Exceedance

5.3.1                 Four (4) Action Level exceedance was recorded for construction noise due to the noise-related complaints received in the reporting month. No Limit Level exceedance was recorded for construction noise monitoring in the reporting month.

5.3.2                No Action and Limit Level exceedance was recorded for construction dust monitoring in the reporting month.


 

6      IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURE

6.1.1      The Contractor had implemented environmental mitigation measures and requirements as stated in the EIA Report, the EP and EM&A Manual. The implementation status of the environmental mitigation measures during the reporting period is summarized in Appendix J. Status of required submissions under the EP during the reporting period is summarised in Table 6.1.

Table 6.1                Status of Required Submission under Environmental Permit

EP Condition

Submission

Submission Date

3.4

Monthly EM&A Report (September 2023)

13 October 2023

 

 


7      FUTURE KEY ISSUES

7.1.1      The main works will be anticipated in the next reporting period are as follow:

Ho Man Tin

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Struct installation and D-wall coring;

¡P          ELS excavation;

¡P          Site and shaft installation.

 

Yau Ma Tei

¡P          Drill and break excavation;

¡P          Drill and blast excavation;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OHVD construction;

¡P          Mucking out from tunnel;

¡P          Site and shaft installation.

 

Ma Tau Kok

¡P          Drill and break excavation;

¡P          TBM pilot tunnel enlargement;

¡P          Underbreak scaling and smoothing works;

¡P          Invert, lining and OVHD construction;

¡P          Mucking out from tunnel and horizontal access;

¡P          Site and shaft installation.

 

Kai Tak Barging Point

¡P          Spoil handling and disposal.

 

Sheung Lok Street

¡P          Concreting and importing fill material by drop pipe.

 

Ma Hang Chung Road

¡P          Concreting.

 

7.1.2      The recommended mitigation measures corresponding to the main works in the next reporting period are listed as follows:

¡P          Good relationship shall be maintained with the nearby sensitive receivers/ stakeholders which may be affected by the construction works such as providing better/ more detail information of the work nature and inform in advance of the works to the nearby residents;

¡P          Any excavated, stockpile of dusty material or load of dusty materials on a vehicle leaving a construction site should be covered entirely by impervious sheeting;

¡P          All construction plants / machineries should be checked / serviced on a regular basis during the courses of construction to minimize the emission of noise generation and eliminate dark smoke emission;

¡P          All C&D materials generated should be transported and stored at temporary storage area. Suitable materials should be sorted for reuse on-site;

¡P          Every vehicle shall be cleaned thorough at the designated wheel washing area onsite;

¡P          Wastewater generated from drilling shall be properly collected for reuse or treated by wastewater treatment facilities before discharge;

¡P          Provision of drip trays for equipment likely cause spillage of chemical / fuel, and provide routine maintenance;

¡P          Erecting temporary noise barrier for noisy Powered Mechanical Equipment (PME) and deployment of Quality Powered Mechanical Equipment (QPME) as many as practicable;

¡P          Conditions in the Environmental Permit and License should be followed;

¡P          All recommended mitigation measures specified in the approved EIA Report and EM&A Manual shall be implemented.

¡P          All vehicles should be cleaned before leaving the construction site to ensure no muddy deposited by them on roads.

 

7.1.3      The environmental monitoring schedule for the next reporting month is provided in Appendix E.


 

8      CONCLUSION AND RECOMMENDATIONS

8.1.1      The 50th Monthly EM&A Report for the Contract No. HY/2018/08 Central Kowloon Route ¡V Central Tunnel summarized the monitoring results and audits findings of the EM&A programme under the issued EP (EP No.: EP-457/2013/D) and in accordance with the EM&A Manual during the reporting period from 01/10/2023 to 31/10/2023.

8.1.2      Construction dust (including 1-hour and 24-hour TSP) and noise monitoring were carried out in the reporting period.

8.1.3      Four (4) Action Level exceedance was recorded for construction noise due to the noise-related complaints received in the reporting month. No Limit Level exceedance was recorded for construction noise monitoring in the reporting month. No Action and Limit Level exceedance was recorded for construction dust monitoring in the reporting month.

8.1.4      Weekly environmental site inspections were conducted during the reporting period. In general, the Contractor had implemented environmental mitigation measures and requirements as stated in the EIA Report, the EP and EM&A Manual.

8.1.5      All complaints received in the last reporting month were finalized.

8.1.6      Four (4) noise-related complaints (i.e. 2nd , 22nd , 24th and 26th October 2023) were received in the reporting month. The investigation reports for the complaints on 2nd , 22nd , 24th and 26th October 2023 were under investigation and the investigation results will be reported in the subsequent Monthly EM&A Report..

8.1.7      No environmental related prosecutions or notification of summons were received in the reporting period.

8.1.8      No environmental non-compliance was recorded in the reporting period.

8.1.9      According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

 

Air Quality Impact

¡P          No specific observation was identified in the reporting month.

 

Construction Noise Impact

¡P          No specific observation was identified in the reporting month.

 

Water Quality Impact

¡P          No specific observation was identified in the reporting month.

 

Waste Management

¡P          No specific observation was identified in the reporting month.

 

Landscape and Visual Impact

¡P          No specific observation was identified in the reporting month.

 

Permit/ Licenses

¡P          NRMM label shell be provided on the generator.